📣 General Mentions
Estimations
All the estimations here assume a 6h/day, 3-day work week
Work Input
Minimum:
2 days | 2h/day
Maximum:
4 days | 8h/day
Work Output
Sprint Length:
1-4 weeks
Adjustment frequency:
weekly
👁️ Overview: 16 weeks (including buffer)
🧠 Prerequisites: 6 weeks
💻 Solana Development: 3 weeks
🎓 Solana Developer Courses: 1 week
👨🏻🍳 The Solana Cookbook: 1 week
⚓️ Anchor: 1 week
🦀 Rust: 2 weeks
📖 The Rust Book & Rustlings: 2 weeks
⏳ Sablier: 1 week
🤓 Sablier Docs: 2 days
🫱🏻🫲 Sablier Contracts: 1 day
👨🏻🔧 Implementation: 8 weeks